Design Process

Typical kitchen project example

  1. Visit our showroom to see a wide range of kitchen displays and door samples. Here we can show you the quality and extra design functions Nolte offer over other kitchen manufacturers, many of which are included as standard with no extra cost.
  2. See fully working kitchen displays to help you choose your appliance and kitchen specification. For example, types of kitchen cabinet lighting and push to open automated doors.
  3. All done at your leisure whilst enjoying a cup of fresh coffee. 
  4. We can then arrange a time for us to visit the site for a full survey.
  5. Here we will discuss with you design ideas that will work in your kitchen and go through additional building, gas and electrical work that you may wish us to undertake.
  6. At your convenience, return to the showroom were we will present you with accurate 3D designs including images. We will then take the time to go through them, making any changes you feel necessary. After which we will give you an accurate cost for the works required.
  7. Once agreed a date will be booked for your installation. This is generally 4 to 6 weeks.
  8. The order will be submitted to Nolte Germany who will program your kitchen plan into their automated manufacturing process. A slot will be allocated and your bespoke kitchen will be assembled and loaded onto a Nolte vehicle ready to be delivered directly to your door.

Typical installation

Day 1:

  • Kitchen is removed, first fix of plumbing and electrical services completed.
  • Water and electricity are off typically off for an hour at the most.  
  • Room prepped for plastering and flooring to be completed same or following day.

Day 2:

  • Kitchen arrives from Nolte 
  • Renovation can be daunting at times, we aim to make this as seamless as possible, which is why your kitchen is delivered the day it is installed, not days or weeks before, inconveniencing yourselves and tradesmen having to work around your new kitchen. 
  • As the room has been professionally prepped and Nolte kitchens come fully factory assembled, the kitchen installation is relatively quick and should be completed within 2 days.

Day 3:

  • Appliances arrive and are installed along with worktops and sinks.
  • Should you have chosen a solid surface such as Dekton or Quartz, the room is templated today and the worktop is fitted typically the following week.
  • A temporary sink can be installed if required.

Day 4:

  • Additional work such as flooring is completed
  • Any remaining waste removed from site and the kitchen is handed over finished to a high standard, complete with any electrical/gas/stove certificates should they be required. 

Now the kitchen is yours to enjoy, with the peace of mind that you have high quality products, professionally installed and covered by warranty and excellent aftercare 